Service offered

JoulePAYS For Heating Optimization

Location

Calicut

Project Tenure

6 Years

Facility Type

Hospital

Start Date

July-2019

Achieving 67% Energy Efficiency by October 2022, Resulting in INR 8.8 Million Yearly Cost Savings.

Design Interventions

  1. Switched from diesel to electric-based hot water system.
  2. Transitioned from a centralized system servicing laundry, sterilization, and domestic hot water uses to a decentralized system servicing individual areas.
  3. Moved from external steam to integrated heating systems.
  4. Implemented preheating boiler feed water for higher efficiencies.

Equipment Interventions

  1. Installed a new 250 kW heat pump for hot water and chilled water generation.
  2. Added 4 new washing machines and 3 new flat-bed press machines in the laundry with in-built electric heaters.
  3. Installed 3 new electric steamers for the sterilization department.

Operations Interventions

  1. Implemented batch-wise monitoring of energy consumption.
  2. Optimized cycle times for washing and sterilization to avoid wastage.
  3. Continuously monitored the heat pump and boilers on DeJoule.
  4. Automated controls of the heat pump and boiler set points for optimal performance.
  5. Optimized running hours of the major equipment.

Project Impact:

INR 8.8 Million

Yearly cost savings for eleminated diesel

Would Joule like to get in touch?